Study: Cross-Trained Crews Could Cut Project Delays
New construction research finds multiskilled workers could help contractors shorten schedules and manage staffing shortages

Contractors struggling to keep projects staffed may benefit from training workers to perform multiple construction tasks, according to new research suggesting multiskilled crews could shorten project schedules by as much as 38%.
The Simplar Foundation released the findings Nov. 12 as part of a six-report research series examining how workforce flexibility affects construction productivity, scheduling and staffing.
Researchers analyzed approximately 89,620 labor hours across 18 construction projects involving 11 contractors. They compared actual project staffing patterns with modeled scenarios restricting each worker to a single trade.
The analysis found that single-trade staffing would have required an estimated 28% to 62% more workdays to complete the same work. Multiskilled crews, by comparison, completed the recorded work in approximately 22% to 38% fewer workdays than the modeled alternative. Researchers also found that single-trade staffing would have created labor shortages in at least one trade on approximately 73% of project workdays, despite sufficient overall crew sizes.
The study emphasized that multiskilling depends on verified worker qualifications and must maintain applicable safety, licensing, quality and supervision standards.
Associated Builders and Contractors funded the research, which was conducted by Simplar Foundation and university partners.
Source: Schedule Duration and Labor-Curve Outcomes (Simplar Foundation, 2026), Study at a Glance.Looking for a reprint of this article?